"G.Solar" LLC, Aragacotn Province, Karmrashen village

Capacity:

800 kW

Location:

Karmrashen, Aragacotn Province

Solar modules՝

AE SOLAR 380 W, monocrystalline 2106 pcs, Germany

Inverter:

SMA Sunny Tripower CORE1 10 pcs and Sunny Highpower Peak1 SHP 75 4 pcs, Germany

Annual electricity production։

1480 MWh

Description
 

The installation of 800 kW power plant was made with 14 blocks (inverters). The Power plant is equipped with accident-prevention  systems to avoid short circuit, non-sinusoidal currents, overvoltages, abrupt voltage changes, zero wire breakage problems, and other failures. In the surrounding area was installed an earth ground loop with a resistance less than 4 ohms for AC and DC circuits.

 

 

"Sun Energy" LLC, Armavir Province, Merdzavan village 3000 kW
"Sun Energy" LLC, Armavir Province, Merdzavan village
The installation of 3 MW power plant was made with 60 blocks (inverters). The Power plant is equipped with accident-prevention systems to avoid short circuit, non-sinusoidal currents, overvoltages, abrupt voltage changes, zero wire breakage problems, and other failures. In the surrounding area was installed an earth ground loop with a resistance less than 4 ohms for AC and DC circuits. The generated capacity is transferred to the "Spandaryan" substation.
04 Dec 2020
3000 kW
"Lusakerti Elit" LLC, Kotayk province, v. Nor Geghi 587 kW
"Lusakerti Elit" LLC, Kotayk province, v. Nor Geghi
The installation of 587 kWt power plant was made with 5 inverters. The Power plant is equipped with accident-prevention  systems to avoid short circuit, non-sinusoidal currents, overvoltages, abrupt voltage changes, zero wire breakage problems, and other failures. In the surrounding area was installed an earth ground loop with a resistance less than 4 ohms for AC and DC circuits.
587 kW
Zar secondary school named after J.Sargsyan 75,85 kW
Zar secondary school named after J.Sargsyan
75,85 kW
"Agarak Terminal" LLC, Syunik province, Agarak 54.72 kW
"Agarak Terminal" LLC, Syunik province, Agarak
54.72 kW